Satara Forest Officer Issues Stop‑Work Order on Adani’s Tarali Project Over Wildlife Clearance

The deputy conservator of forests (DCF) for Satara, Amol Satpute, has issued a stop‑work order to the project manager of Adani Renewable Energy One Ltd. The order follows the commencement of work on the 1,500MW Tarali pumped‑storage project in Patan taluka without prior approval from the National Board for Wildlife (NBWL). Adani Group says it has submitted a proposal for wildlife clearance to the board.
The DCF’s action comes after a separate October report that Adani Green Energy Ltd (AGEL), which is executing the project, had reduced the declared project cost from Rs 5,675 crore to Rs 56.75 crore when reporting to the state government, allegedly to lower statutory environmental obligations. On November 13, the DCF issued a show‑cause notice under the Wildlife (Protection) Act, 1972, and the Maharashtra Tree Felling (Regulation) Act, 1964, demanding a written explanation for initiating the project without valid NBWL permission. The notice warned that continued work would trigger legal and penal action under forest laws and requested details on any tree‑felling permissions, including the number of trees approved and the original permits.
AGEL’s spokesperson stated that all required land‑use and statutory approvals had been obtained. The company said that after receiving environmental clearance in February 2025, the Maharashtra Pollution Control Board issued consent to establish on April 7, 2025, allowing construction to begin. The spokesperson added that the wildlife clearance process had been initiated and that the proposal for survey and investigation activities was submitted in January 2025, recommended by the state board, and is now under NBWL consideration. The company also claimed that no project component falls within a protected area or forest land, citing a NOC received on January 23, 2024.
On October 30, Satara’s honorary wildlife warden, Rohan Bhate, highlighted an alleged discrepancy in the project cost reported to the state government, noting it was listed as Rs 56.75 crore instead of Rs 5,675 crore. Bhate requested an independent inquiry, arguing that an understated cost could amount to misrepresentation and affect wildlife conservation contributions linked to the project value. The MoEFCC’s environmental clearance issued on February 11, 2025, records the project cost at Rs 5,675 crore and lists Rs 39.3 crore for the environmental management plan and Rs 27.5 crore for recurring operation and maintenance.
Reports indicate that on September 7, AGEL’s chief operating officer, Naresh Telugu, submitted a letter to the principal chief conservator of forests (wildlife), Maharashtra, along with a notarised undertaking on a Rs 500‑stamp paper, citing the project cost as Rs 56.75 crore. The undertaking claimed the figure was based on an “analogous estimation” used while submitting “Part IV,” and committed to mitigation and conservation measures. AGEL denied that the figures were used to reduce statutory obligations, stating they related only to preliminary investigations and surveys.
Bhate noted that the difference between the estimated total project cost in available documents and the amount stated in the notarised undertaking is substantial, differing by a factor of 100. He explained that the administration of the Sahyadri Tiger Reserve had previously communicated that 4% of the total project cost (approximately Rs 227 crore) was required to be deposited in the account of the STR Conservation Foundation for wildlife conservation. Based on the revised cost of Rs 56.75 crore, 1% would be Rs 56.75 lakh, with the remaining 3% payable after NBWL clearance. Bhate said that if the project cost had been deliberately understated, it would raise serious concerns about misrepresentation of financial information to the government and its impact on wildlife conservation contributions. He called for an investigation to determine whether the project cost was correctly assessed, whether the applicable contribution requirements were properly implemented, and whether the decision to calculate the contribution on the basis of Rs 56.75 crore was supported by relevant rules, official records, and approved conditions.
Frequently asked questions
Why did the Satara DCF issue a stop‑work order on Adani’s Tarali project?
Because work began on the 1,500MW Tarali pumped‑storage project in Patan taluka without prior approval from the National Board for Wildlife (NBWL).
What cost discrepancy was raised by Satara’s wildlife warden?
The warden noted that the project cost was reported as Rs 56.75 crore to the state government instead of the Rs 5,675 crore recorded in the MoEFCC clearance.
What approvals has Adani Renewable Energy One Ltd. claimed to have received for the Tarali project?
Adani says it received environmental clearance in February 2025, consent from the Maharashtra Pollution Control Board on April 7, 2025, and a NOC on January 23, 2024, and that it has submitted a wildlife clearance proposal to the NBWL.